Dholera airport flights: no airline or schedule yet, and what must happen first

Updated 11 November 2026. Compiled by the DholeraPulse desk from the sources listed at the end of this page.

There are no flights to Dholera airport yet. As of 13 November 2026 no airline, route or schedule has been announced. A calibration landing took place and AAI signed an operation and maintenance agreement on about 4 November 2026. On 16 October 2026 officials said the airport is expected to be operational by the end of 2026.

From runway to first passenger flight, step by step

Step toward the first passenger flightStatusDate and source
Runway builtReported complete: 3,200 m runway, Code 4E, single runway in phase 1Fact base; ministry review reported July 2026
First aircraft landingDone: an AAI calibration or trial landing on 4 June 2026 near Pipli village. It shows the runway can be used; it does not open the airportGujarat Samachar and trade reports, June 2026
Operation and maintenance agreementSigned between AAI and Dholera International Airport Company Ltd (DIACL); no terms or opening date givenAbout 4 November 2026, Indian Masterminds (3 Nov) and CAPA (4 Nov)
Official target for operationsExpected to be operational by the end of 2026, later than the earlier September to October 2026 targetChief Minister's review, 16 October 2026, as reported by NewKerala
DGCA aerodrome licenceNo report found of it being issuedNot stated in the record, 13 November 2026
An airline scheduleNone announcedNot stated in the record, 13 November 2026

Which airlines will fly from Dholera?

No airline has announced a route to Dholera in any official release or major newsroom report we found. Some blogs and portals say named airlines are in discussion. We do not repeat those names, because none of them points to a company statement or a regulator record.

The pattern in India is that an airline files a schedule only after an airport has its licence and a firm opening date. Neither exists for Dholera yet.

Who owns and runs the airport

Dholera International Airport Company Ltd (DIACL) is the company that owns the airport. The Airports Authority of India holds 51 per cent, the Gujarat government 33 per cent and NICDC 16 per cent. The operation and maintenance agreement signed on about 4 November 2026 gives AAI the job of running it, with no terms published.

Why the date keeps moving

The opening target has slipped more than once. In July 2026 the ministry aimed for operations within three months. By 16 October 2026 the target given to the Chief Minister was the end of 2026. Our record treats every date as a target until a licence and a first scheduled flight exist. Our airport page keeps the full timeline.

How people reach Dholera today

Until Dholera opens, a traveller flying in uses Ahmedabad airport, which is about 80 km from the Dholera airport site and about 100 km from Dholera by road. The Ahmedabad-Dholera Expressway was inaugurated on 31 March 2026. See how to reach Dholera and the expressway page.

What to watch for

Four dated events would change this page: a DGCA aerodrome licence, an airline announcing a route, a notified opening date and a first scheduled passenger flight. Our latest news log records each one when it is reported, with the source.

Questions people ask

Are there flights to Dholera?

No. As of 13 November 2026 no scheduled passenger flight operates to or from Dholera airport. A calibration landing took place on 4 June 2026, but the airport is not open.

Which airline will operate from Dholera airport?

No airline has been announced. Unsourced blogs name airlines, but we found no airline or regulator statement. We will record an announcement here when one is made.

When will the first flight from Dholera take off?

No date is fixed. Officials said on 16 October 2026 that the airport is expected to be operational by the end of 2026. That is a target, not a scheduled flight.

Has Dholera airport got a licence?

We found no report of a DGCA aerodrome licence being issued as of 13 November 2026. The licence status is not stated in the record.

Who will run Dholera airport?

AAI signed an operation and maintenance agreement with DIACL, the airport company, on about 4 November 2026. DIACL is owned 51 per cent by AAI, 33 per cent by the Gujarat government and 16 per cent by NICDC.

Which airport do I use to reach Dholera now?

Ahmedabad airport, about 80 km from the Dholera airport site. The road journey from Ahmedabad is about 100 km, and the expressway cut the drive to about 40 minutes to 1 hour, as reported.

Read next

Sources

  1. Indian Masterminds, AAI and DIACL operation and maintenance agreement (3 November 2026)
  2. CAPA, AAI and DIACL sign O&M agreement for Ahmedabad-Dholera airport (4 November 2026)
  3. NewKerala, Gujarat CM takes stock of projects in Dholera region (16 October 2026)
  4. All India Radio, Dholera International Airport to become operational in three months (14 July 2026)