Home › Timeline
Timeline

Dholera milestones, dated and sourced

From the 1930 Dholera Satyagraha to the Tata semiconductor fab and the 2026 expressway. 30 verified milestones. Reported and target dates are labelled honestly.

6 Apr 1930 Done

Dholera Satyagraha begins

Following Gandhi breaking the salt law at Dandi on 6 April 1930, Amritlal Seth led about 21 satyagrahis in a salt-law civil-disobedience action at Dholera port. A larger contingent under Balwantrai Mehta followed around 13 April.

Overview Gujarati Vishwakosh (reported)
1955-1960 Done

Lothal excavated nearby

The Archaeological Survey of India excavated the Indus Valley (Harappan) site of Lothal, home to what the ASI calls the world's earliest known dock, in the same Ahmedabad district about 36 km from Dholera (approximate).

Geography ASI / Wikipedia (reported)
2007 Done

GIFT City announced (comparator)

Gujarat International Finance Tec-City, the state's finance-focused smart city near Gandhinagar, was announced in 2007. It later became a comparator benchmark for Dholera as a greenfield smart city.

Overview Wikipedia (reported)
2009 Done

Gujarat SIR Act passed

The Gujarat Special Investment Region Act, 2009 established the legal basis for Special Investment Regions in the state, the framework under which Dholera SIR was later constituted.

Government Gujarat govt / DICDL
2009 Done

Delhi-Mumbai Industrial Corridor announced

The Delhi-Mumbai Industrial Corridor (DMIC) was announced in 2009, with Dholera positioned as one of its nodes (often reported as its largest node).

Government Business Standard / DMIC (reported)
2011-2015 Done

Land transfers for the SIR

Land transfers for the SIR proceeded between 2011 and 2015 before farmer petitions led to a court stay. A 2017 report later described DMIC progress as a tale of abandonments and delays.

Government Business Standard 2017 (reported)
2013 Done

DMIC and Dholera publicly championed

Dholera and the DMIC were publicly championed in a 2013 announcement, one of the specific milestones cited when tracing the project's timeline.

Government Business Standard / press (reported)
April 2015 Done

GIFT City established (comparator)

GIFT City was established on 10 April 2015 and is described as India's first operational greenfield smart city and IFSC, a frequent point of comparison for Dholera.

Overview Wikipedia (reported)
2015 Done

Gujarat HC stays SIR land acquisition

The Gujarat High Court stayed SIR land acquisition in 2015 after farmer petitions. A 2017 report later found only about 290 of 900-plus sq km had been secured at that point.

Government Business Standard 2017 (reported)
28 Jan 2016 Done

DICDL incorporated

Dholera Industrial City Development Ltd (DICDL), the special-purpose vehicle that builds the city, was incorporated on 28 January 2016, owned Gujarat govt 51 percent and Central govt 49 percent.

Government DICDL / dholera.gujarat.gov.in
April 2018 Done

Dholera solar park approved

The Dholera Ultra-Mega Solar Power Park was approved around April 2018, with an ultimate announced target of 5,000 MW (5 GW) and Phase-I of 1,000 MW sanctioned.

Mega-projects CEA / project reports (reported)
Jan 2021 Target

Ahmedabad-DSIR MRTS reported approved

An Ahmedabad-DSIR MRTS (mass rapid transit) link was reported approved around January 2021. Its current status is unclear and likely overlaps with the 2026 semi-high-speed rail plan.

Connectivity Press (reported, status unclear)
Sept 2022 Done

Vedanta-Foxconn MoU signed

Vedanta and Foxconn signed an MoU with Gujarat in September 2022, a JV widely cited at about 19.5 billion US dollars. This was a project value, not committed capital, and the venture never built anything.

Mega-projects Business Standard (reported)
10 Jul 2023 Done

Foxconn exits the JV

Foxconn withdrew from the Vedanta joint venture on 10 July 2023, ending the collapsed semiconductor project. It is now historical, not an active investment at Dholera.

Mega-projects Business Standard (reported)
Jan 2024 Done

Airport terminal EPC contract awarded

The Dholera International Airport terminal EPC contract of about Rs 333 cr was reported awarded in January 2024, alongside Phase-1 civil works to Varaha Infrastructure at about Rs 636.45 cr.

Connectivity Project reports (reported)
29 Feb 2024 Done

Tata fab gets Cabinet approval

The Union Cabinet approved the Tata Electronics + PSMC semiconductor fab on 29 February 2024 under the India Semiconductor Mission, with investment of Rs 91,000 cr (about 11 billion US dollars) and capacity up to 50,000 wafers per month.

Mega-projects PIB PRID 2108602
Mar 2024 Done

Tata fab ground-breaking

Ground-breaking for the Tata Semiconductor Manufacturing fab took place in March 2024. Construction later progressed after a late-2025 redesign for local soil conditions.

Mega-projects Tata / project reports (reported)
2024 Underway

ABCD Building and ICCC reported operational

The ABCD Building (Administrative cum Business Centre for Dholera) in the TP2 Knowledge and IT Zone, housing the Integrated Command and Control Centre that acts as the smart-city brain, was reported structurally complete and operational. The exact inauguration date is unknown.

Mega-projects DICDL interview (reported)
5 Mar 2025 Done

ISM Fiscal Support Agreement signed

The India Semiconductor Mission Fiscal Support Agreement for the Tata fab was signed on 5 March 2025, with ISM covering 50 percent of eligible cost. PIB cites Rs 91,526 cr for the project.

Money PIB / ISM
31 Mar 2026 Done

Ahmedabad-Dholera Expressway inaugurated

The 109 km, 4-lane greenfield access-controlled Ahmedabad-Dholera Expressway was reported inaugurated by PM Modi on 31 March 2026 and is operational, cutting travel time toward roughly 40 minutes to 1 hour (sources vary).

Connectivity NHAI / press (reported)
13 May 2026 Target

Semi-high-speed rail cleared by CCEA

The Ahmedabad(Sarkhej)-Dholera semi-high-speed rail line was reportedly cleared by the CCEA around 13 May 2026, at about Rs 20,667 cr for a roughly 134 km double line, targeted for 2030-31.

Connectivity Press (reported/target)
17 May 2026 Done

ASML-Tata lithography MoU

Tata signed a lithography MoU with ASML on 17 May 2026 for the Dholera fab, covering advanced lithography tooling.

Mega-projects Tom's Hardware (reported)
Mid 2026 Underway

Tata fab civil about 50 percent complete

As of mid-2026 the Tata fab civil works were reported about 50 percent complete after a late-2025 redesign for soil conditions. First chip is targeted for 2026-27, a target with no source confirming a chip produced.

Mega-projects Project reports (reported)
2026 Done

About 300 MW solar operational

About 300 MW of solar capacity is operational at Dholera, including a Tata Power plant with 873,012 monocrystalline modules over 1,320 acres. Phase-I of 1,000 MW is sanctioned, with 700 MW more targeted by March 2027.

Money CEA Sept 2025 / Tata Power (reported)
2026 (target) Target

Dholera International Airport opening targeted

The airport's opening is a repeatedly slipping target. As of 14 July 2026 the Union Aviation Minister reportedly said it was about 80 percent complete with operations likely Sept-Oct 2026. No firm opening is confirmed as achieved.

Connectivity Press Jul 2026 (target, never firm)
2027 (target) Target

Solar Phase-I 1,000 MW targeted

The remaining 700 MW of the sanctioned 1,000 MW Phase-I solar capacity is targeted for completion by March 2027, awarded to developers including Tata Power, Vena, ReNew, SJVN and TEQ Green, subject to tariff and GERC disputes.

Money CEA Sept 2025 (target)
2026-27 (target) Target

Tata fab first chip targeted

The Tata fab's first chip is targeted for 2026-27. This is a target only, with no source confirming a chip has been produced.

Mega-projects Tata / ISM (target)
2030 (target) Target

Solar park 5,000 MW ultimate target

The ultimate announced target for the Dholera solar park is 5,000 MW (5 GW), roughly by 2030. This is a long-range target, not installed capacity.

Money Project announcements (target)
2030-31 (target) Target

Semi-high-speed rail service targeted

The Ahmedabad-Dholera semi-high-speed rail is targeted to be in service by 2030-31, offering a roughly 45-minute journey. A cited 220 km/h speed is single-sourced and flagged as suspect.

Connectivity Press (reported/target)
~2040 (target) Target

Full phased build-out targeted

Full development of the roughly 920 sq km planning envelope is targeted over about 30 years, reaching an end-year stated inconsistently as 2040 or 2042, with promotional targets near 1 million population and about 800,000 jobs. All are reported targets.

Overview DICDL / promo (target)