Dholera dates to watch from the end of 2026 through 2027, and three events with no date yet
Updated 11 November 2026. Compiled by the DholeraPulse desk from the sources listed at the end of this page.
Three Dholera targets fall between the end of 2026 and August 2027: the airport (end of 2026), the remaining 700 MW of solar (March 2027) and a DHL chip logistics warehouse (about August 2027). Three more events, a jantri revision, a rail EPC contract award and a desalination award, have no date in the record.
The calendar
| Order | What to watch | Target date | Who stated it, and when | Kind of source | What would confirm it |
|---|---|---|---|---|---|
| 1 | Dholera airport operational | End of 2026 | Chief Minister's review, reported 16 October 2026 | Reported by a news wire | A licence from the aviation regulator and a published airline schedule |
| 2 | Remaining 700 MW of solar Phase I | March 2027 | Central Electricity Authority quarterly report, September 2025 | Government report | An updated commissioning figure in a later monitoring report |
| 3 | DHL semiconductor logistics warehouse | About August 2027 | Electronics For You, 15 October 2026 | Reported by trade press | A company release or an inauguration notice |
| 4 | Jantri revision | Date not stated in the record | No notification found as of 11 November 2026 | No source on record | A Gujarat government notification of new rates |
| 5 | Rail contract award or construction start | Date not stated in the record | Approval on 13 May 2026; an EPC tender reported on 3 August 2026 (India Shipping News) | Government release (approval only) | An award notice or a construction announcement from Western Railway |
| 6 | Desalination plant award | Date not stated in the record | A 200 MLD plan at the stage of a feasibility study and project report, reported 18 July 2026 | Reported by a regional newsroom | A tender notice, then an award notice naming a bidder |
1. Dholera airport operational
- TargetEnd of 2026
- Slipped fromSeptember to October 2026
- Latest news4 November 2026 agreement with AAI
This is the date closest to today. The airport has already missed December 2025 and a September to October 2026 aim. The record does not yet show a licence or a schedule, so the useful sign is a published schedule, not another target.
2. Remaining 700 MW of solar Phase I
- Sanctioned1,000 MW
- CommissionedAbout 300 MW
- Developers namedTata Power, Vena, ReNew, SJVN and TEQ Green
The September 2025 report said the work was delayed by tariff disputes, so March 2027 is a target that has already depended on those disputes being settled.
3. DHL semiconductor logistics warehouse
- Initial investmentAbout Rs 50 crore
- TargetAbout August 2027
Coverage traces to one newspaper report and no DHL release has been found. Treat it as a reported plan.
Why these dates can move
Dholera's own record shows how targets move. The airport's first aim in the record was December 2025, then September to October 2026, then the end of 2026. A date on this page is the newest one a source has stated, so it can change as the source updates.
What is not on this list
A Vibrant Gujarat global summit is not listed as a date, because no dated announcement for one has been found. Broker pages also name many dates. None is included unless a named public source states it.
How to use the calendar
- When someone quotes a Dholera date to you, find it in the table and look at the tier.
- Ask what record would confirm it, and look for that record yourself.
- Check the GujRERA registration, title and price for any plot before you pay.
What this list cannot tell you
This calendar lists targets that public sources have stated. It cannot tell you that any date will be met, or what any date means for the value of a particular plot.
Questions people ask
When will Dholera airport start operations?
The target reported on 16 October 2026 is the end of 2026. The airport is not open as of 11 November 2026. No licence or airline schedule has been reported, so a published schedule is the sign to look for.
What will happen in Dholera in 2027?
In the record, the dated 2027 targets are the remaining 700 MW of solar Phase I in March 2027 and a DHL chip logistics warehouse around August 2027. Both are targets. Other 2027 events, such as a rail contract award, have no date stated.
When will the Tata fab in Dholera begin?
Commercial production was reported in July 2026 as expected around mid-2028, which is after the window of this page. No source says a chip has been produced as of 11 November 2026.
Will Gujarat revise jantri rates for Dholera in 2027?
No revision has been notified as of 11 November 2026. Available reports say the rates doubled on 15 April 2023 still apply, and a revision is expected. No date is stated, so this page lists it without one.
Read next
Sources
- NewKerala: Gujarat CM takes stock of projects in Dholera region (16 October 2026)
- Central Electricity Authority: solar parks quarterly report (September 2025)
- Electronics For You: DHL to set up dedicated semiconductor logistics facility in Gujarat by 2027 (15 October 2026)
- TrendForce: Tata fab reportedly to launch at 90nm, commercial production mid-2028 (20 July 2026)