Dholera tracker board, November 2026: airport, expressway, fab, rail, solar and water
Updated 11 November 2026. Compiled by the DholeraPulse desk from the sources listed at the end of this page.
As of 11 November 2026: the airport is not open and is targeted for the end of 2026; the expressway was inaugurated on 31 March 2026; the Tata fab is under construction with commercial production reported for mid-2028; the rail line is approved with no construction start reported; solar is about 300 MW of 1,000 MW; water is at plan stage.
Six trackers, one row each
| Order | Tracker | Latest dated reading | Date of reading | Kind of source | Next thing to watch |
|---|---|---|---|---|---|
| 1 | Expressway | Inaugurated; 109 km, built by NHAI | 31 March 2026 | Reported by national press | A toll notification for cars, none found in the record |
| 2 | Solar park | About 300 MW commissioned of 1,000 MW sanctioned in Phase I; 5,000 MW is the long-range target | 30 June 2026 government monitoring report | Government report | The 700 MW still under development, targeted March 2027 |
| 3 | Airport | Not open. Trial landing, operation agreement with AAI reported, target end of 2026 | 4 November 2026 | Reported by news outlets | A licence from the aviation regulator and an airline schedule, neither reported |
| 4 | Tata fab | Under construction. Commercial production reported for mid-2028. INOX India began initial piping work | 6 November 2026 | Company and news reports | A company or ministry statement on first output |
| 5 | Rail | Approved at Rs 20,667 crore for 134 km, target up to 2030-31. No construction start reported | 13 May 2026 | Government release (PIB) | A tender or a construction start |
| 6 | Water | A 2,200 million litre raw water reservoir announced at a Rs 438.74 crore estimate; a 200 MLD desalination plant at report stage | 3 to 6 November 2026 | Reported by a regional newsroom | The name of the contractor, not yet stated |
1. Expressway
- Length109 km
- AgencyNHAI
- Reading31 March 2026
Of the six trackers this is the one buyers can drive on. A Gujarat High Court order, reported by Swarajya on 29 April 2026, cancelled the acquisition of two extra plots in Bholad village for the road. No effect on the road's use has been reported.
2. Solar park
- CommissionedAbout 300 MW
- Sanctioned Phase I1,000 MW
- Source30 June 2026 NICDC monitoring report
The 5,000 MW figure is a target for around 2030, not capacity in operation. No newer operating figure has been found since the June report.
3. Airport
- Runway3,200 m, Phase I
- StatusNot open
- TargetEnd of 2026, reported 16 October 2026
A trial landing was reported on 4 June 2026. The agreement signed with the Airports Authority of India, reported on 4 November 2026, gave no terms or opening date.
4. Tata fab
- InvestmentAbout Rs 91,000 crore
- CapacityUp to 50,000 wafers a month
- Commercial productionMid-2028, reported
No completion percentage is printed here because the only figures in the record come from broker pages. Reports differ on the first chip size: a July 2026 report said mostly 90 nm at launch, and the company has said its plan spans 28 to 110 nm.
5. Rail
- Length134 km
- CostAbout Rs 20,667 crore
- LinksAhmedabad, Dholera SIR, the airport and Lothal
A separate 23 km Bhimnath to Dholera logistics line was described at the 16 October 2026 review as being developed. No tender has been reported for either line.
6. Water
- Reservoir2,200 million litres, 18 months to build
- EstimateRs 438.74 crore
- Desalination200 MLD plan at report stage
The 200 MLD seawater desalination plan was reported on 18 July 2026 as at the stage of appointing a consultant for a feasibility study and a detailed project report. No contractor has been named for the reservoir or the desalination plant.
How to read the board
A row moves forward only when a dated record changes it. A project can be physically ahead of its paperwork or behind it, so the board shows both the reading and the tier of the record behind it.
The order in the table is by how much of each project is in use today. It is not a ranking of which project matters most to land values.
Where to check each reading yourself
- Rail and cabinet decisions: the Press Information Bureau at pib.gov.in.
- Airport and fab company releases: Airports Authority of India and Tata Electronics newsrooms.
- Tenders and plans: the DSIRDA and DICDL portal at dholera.gujarat.gov.in.
- Project registrations: the GujRERA portal at gujrera.gujarat.gov.in.
Before you buy
A tracker reading is about public projects. For any plot, verify the GujRERA registration, the title and the price for that exact plot.
What this list cannot tell you
This board shows reported progress on public projects. It cannot tell you whether a plot you are offered is registered, what it costs, or when any project will reach its target.
Questions people ask
What is the status of Dholera airport in November 2026?
Not open. The target reported on 16 October 2026 is that it is operational by the end of 2026. An operation and management agreement with the Airports Authority of India was reported on 4 November 2026. No licence or airline schedule has been reported.
How much solar power is running in Dholera?
About 300 MW is commissioned according to the 30 June 2026 monitoring report, out of 1,000 MW sanctioned for Phase I. The 5,000 MW figure is a long-range target. We have found no newer operating number.
When will the Tata fab in Dholera start producing?
Commercial production was reported in July 2026 as expected around mid-2028. No source in our record says a chip has been produced.
Has construction of the Ahmedabad-Dholera rail line started?
No start has been reported as of 11 November 2026. The Union Cabinet approved the 134 km line on 13 May 2026 at about Rs 20,667 crore with a target of up to 2030-31.
Is there a toll on the Ahmedabad-Dholera expressway?
The record shows tolling is planned on a closed system, but no rate for cars on this stretch has been found in a notification. We print no figure until one is published.
Read next
Sources
- NICDC Delivery Monitoring Unit report (30 June 2026)
- NewKerala: Gujarat CM takes stock of projects in Dholera region (16 October 2026)
- CAPA: AAI and DIACL sign O&M agreement (4 November 2026)
- DeshGujarat: Dholera to get raw water reservoir (3 November 2026)
- DeshGujarat: Dholera to set up 200 MLD seawater desalination plant (18 July 2026)
- Press Information Bureau (13 May 2026)