Dholera data centre plan: what Gujarat has announced and what is not yet built

Updated 13 November 2026. Compiled by the DholeraPulse desk from the sources listed at the end of this page.

Gujarat launched the Viksit Gujarat Data Centre Policy 2026-29 on 9 July 2026 and notified it on 7 August 2026. It targets 7.5 GW of hyperscale green AI data centre capacity and names Dholera as a hub. Officials said 14 companies have shown interest. One company, L&T Vyoma, signed a feasibility-stage MoU in February 2026 for 250 MW at Dholera. No Dholera data centre has been reported as built, as of 13 November 2026.

The data centre story in dated steps

DateWhat was announcedWho said itHow firm it is
About 20 February 2026L&T Vyoma signed an MoU with the Gujarat Department of Science and Technology to explore a 250 MW green AI-ready data centre at Dholera, with a stated investment of Rs 25,000 crore and a detailed feasibility study firstMoU signing, reported by The Blunt TimesAn MoU at feasibility stage, not a final investment decision
9 July 2026Gujarat launched the Viksit Gujarat Data Centre Policy 2026-29 and said it had received proposals from 14 companies, with first-phase investment above Rs 6 lakh crore expectedState government, reported by PTI via Outlook BusinessA launch and an expectation, not a signed investment
9 July 2026The Science and Technology Minister said Dholera alone is expected to house a 7 to 8 GW cluster worth about Rs 6 to 7 lakh croreMinister's statement at the launchA projection
9 July 2026The Deputy Chief Minister said requests seek nearly twice the 7.5 GW target and that Dholera is set to become a data centre cityMinister's statement at the launchA claim about interest, not about capacity built
7 August 2026The government resolution formally notified the policy: 7.5 GW target, at least 51 per cent of power from renewable and green sources, Dholera identified as one of the largest hyperscale green AI data centre hubsGovernment resolution, reported by IANSThe policy is in force; projects still need approval
As of 13 November 2026No land allotment, construction start or power-supply agreement for a Dholera data centre appears in the reports we readOur review of the recordNot stated in the record

Download this table (CSV). Last checked 13 November 2026. Free to quote with a link to this page.

What the policy says about Dholera

The policy sets a target of 7.5 GW of hyperscale green AI data centre capacity by 2029 across the state. The notification of 7 August 2026 says Dholera has been identified for development as one of the world's largest hyperscale green AI data centre hubs. It links that to the planned urban infrastructure of the Dholera SIR and to GIFT City.

A policy is a set of rules and incentives. It does not by itself build a data centre, secure power or bring a customer.

Incentives named in the policy

IANS lists the types of incentive: capital subsidy, interest subsidy, power tariff subsidy, reimbursement of electricity duty, exemption from stamp duty and registration fees, SGST reimbursement, and help towards captive desalination plants. It also names non-fiscal help such as faster approvals, flexible building rules and additional floor space index. We have not read the government resolution itself, so we do not print rates or eligibility thresholds. Figures for subsidy rates that circulate online come from sources we do not rate as reliable.

Why power and water decide this

The policy requires at least 51 per cent of a project's operating electricity to come from renewable and green sources. The government pointed to about 74 GW of installed power capacity in Gujarat. Water is the other constraint, and the policy mentions help for captive desalination. Dholera's own desalination plans are tracked on our November 2026 trackers page, and the existing water and solar facts sit on our water and solar park pages.

What has not been reported

As of 13 November 2026 we found no report of a land allotment for a data centre in Dholera, no construction start and no power-supply agreement. The one named company is L&T Vyoma, whose February 2026 MoU for a 250 MW campus starts with a feasibility study of land, infrastructure and sustainability, so it is not yet a decision to build. Fourteen interested companies is a count of expressions of interest. The minister's range of 7 to 8 GW is a target for the cluster, and the minister's own figure of Rs 70,000 crore to Rs 1 lakh crore per GW shows how large each project would be if it happened.

What this means for someone watching Dholera

Data centres are a new line in the Dholera story, next to the Tata semiconductor fab and the supply chain around it. They are a reason to watch for dated, named announcements, such as an allotment, a power agreement or a groundbreaking, and not a reason to expect a particular outcome for any plot. Our latest news log records those events as they are reported.

Dholera data centre status in one list

  • Policy: launched 9 July 2026, notified 7 August 2026, target 7.5 GW statewide.
  • Named company: L&T Vyoma, 250 MW MoU of February 2026, feasibility stage.
  • Interest: 14 company proposals reported at launch.
  • Not reported: land allotment, construction start, power-supply agreement.

Check this list against the latest news log before you act on it, since a single named allotment would change the status.

Questions people ask

Is there a data centre in Dholera?

None has been reported as built as of 13 November 2026. The state has notified a policy that identifies Dholera as a hub and says 14 companies have shown interest, and L&T Vyoma signed a feasibility-stage MoU for 250 MW in February 2026. Interest and an MoU are not construction.

What is the Viksit Gujarat Data Centre Policy 2026-29?

It is Gujarat's data centre policy, launched on 9 July 2026 and notified on 7 August 2026. It targets 7.5 GW of hyperscale green AI data centre capacity and offers fiscal and non-fiscal incentives, with Dholera named as a hub.

How much capacity is planned for Dholera?

The Science and Technology Minister said on 9 July 2026 that Dholera alone is expected to house a cluster of 7 to 8 GW. That is a projection stated at the launch, not capacity under construction.

Which companies will build data centres in Dholera?

Only L&T Vyoma has been named, through its February 2026 MoU for a 250 MW campus that begins with a feasibility study. Officials said around 14 hyperscale investors expressed interest in the state policy, and those companies were not named in the reports we read.

Does a data centre policy raise Dholera plot prices?

We do not state any price effect. No sourced figure links the policy to land prices, and returns are never promised on this site.

What power must a Gujarat data centre use?

Eligible projects must source at least 51 per cent of their operational electricity from renewable and green sources, according to IANS on 7 August 2026.

Read next

Sources

  1. IANS, Gujarat notifies data centre policy to build 7.5 GW green AI capacity by 2029 (7 August 2026)
  2. PTI via Outlook Business, Gujarat launches Data Centre Policy (9 July 2026)
  3. The Blunt Times, Gujarat signs Rs 25,000 crore MoU for 250 MW AI data centre at Dholera (February 2026)
  4. Official Dholera portal (DSIRDA and DICDL) (checked 13 November 2026)